Road Construction Updates

Procter Street Extension

Repair and reconstruction of the Procter Street Extension began on August 27, 2019. Currently the AE-P Emulsion (Prime Oil) was placed on the base surface and will cure for 48 hours. Asphalt surfacing and paving is scheduled to begin on Thursday, October 10, 2019.