LD Construction began the 6-month street rehabilitation program on June 21, 2021, to clean and reshape ditches in the green-highlighted areas.

ACTIVITY | START | END | STREETS |
Project Start | 6/21/2021 |
|
|
Section 1 | 6/21/2021 | 07/30/2021 | (63rd Street, Katy Avenue, Hazel Street, and 60th Street) |
Section 2 | 8/2/2021 | 9/17/2021 | (Sassine Avenue, Weaver Street, Louisiana Avenue, Alabama Avenue, Mississippi Avenue, Davis Avenue) |
Section 3 | 9/20/2021 | 10/22/2021 | (Shirley Street, Pastel Avenue) |
Section 4 | 10/25/2021 | 12/3/2021 | (50th Street, Houston Avenue, Linkwood Avenue, Austin Avenue) |
Section 5 | 12/6/2021 | 1/14/2022 | (Austin Avenue, Dallas Avenue, 14th Street) |