[ARCHIVED] Public Works Street Repair Projects June 2021 - January 2022

LD Construction began the 6-month street rehabilitation program on June 21, 2021, to clean and reshape ditches in the green-highlighted areas.

 Street Rehabilitation Program Sections1-5

ACTIVITY

START

END

STREETS

Project Start6/21/2021

Section 16/21/202107/30/2021(63rd Street, Katy Avenue, Hazel Street, and 60th Street)
Section 28/2/20219/17/2021(Sassine Avenue, Weaver Street, Louisiana Avenue, Alabama Avenue, Mississippi Avenue, Davis Avenue)
Section 39/20/202110/22/2021(Shirley Street, Pastel Avenue)
Section 410/25/202112/3/2021(50th Street, Houston Avenue, Linkwood Avenue, Austin Avenue)
Section 512/6/20211/14/2022(Austin Avenue, Dallas Avenue, 14th Street)