Construction Update on Bluebonnet Avenue
- Setting up forms and preparing for concrete pour on east side of Bluebonnet Avenue from Marshall Avenue to St. Augustine Avenue.
- Pour concrete on east side of Bluebonnet Avenue from Marshall Avenue to St. Augustine Avenue.
- Excavate and set forms on east side of Bluebonnet Avenue from St. Augustine Avenue to Gulfway Drive and inside lanes at DeQueen Boulevard intersection.
Future Outlook
- Continue setting up forms and tying steel for east side of Bluebonnet Avenue from St. Augustine Avenue to Gulfway Drive and inside lanes at DeQueen Boulevard intersection.
- Working on all side street transitions on east side of Bluebonnet Avenue.
- Prepare and finish full depth concrete repair on east side of Bluebonnet Avenue near 19th Street.