PUBLIC SERVICE ANNOUNCEMENT-Kansas City Southern Making Repairs
KCS Railroad Company continues its replacement of rail and the rebuilding of crossings throughout the City of Port Arthur. KCS has been scheduled to perform this work from November 22, 2020, through December 20, 2020, which will occur between 6:00 a.m. and 6:00 p.m. each scheduled day.
Location | Nearest Cross Street1 | Nearest Cross Street2 | Work to be Completed | Date of Construction |
60th Street | 9th Avenue | Twin City Hwy (Hwy 347) | Rail Replacement | 12/06 & 12/07 |
Procter Extension | Main Avenue | Taft Avenue | Rebuild Crossing | 12/06 & 12/07 |
Taft Avenue | Gulfway Drive (Hwy 87) | Valley Forge | Rebuild Crossing | 12/08 & 12/09 |
32nd Street | Pure Atlantic Road | Redbud Road | Rebuild Crossing | 12/08 & 12/09 |
Terrell Street | Pure Atlantic Road | Redbud Road | Rebuild Crossing | 12/09 & 12/10 |
Pinetop Road | Pure Atlantic Road | Atlantic Road | Rebuild Crossing | 12/15 & 12/16 |
39th Street | Pure Atlantic Road | Atlantic Road | Rebuild Crossing | 12/15 & 12/16 |
60th Street | 9th Avenue | Twin City Hwy (Hwy 347) | Rebuild Crossing | 12/19 & 12/20 |
To aid in the identification of work zones, the approved traffic control plans are listed below and the City's Traffic Engineer has comprised a Google map with each location marked (https://www.google.com/maps/d/u/0/edit?mid=1ozz1szN8IXF90rpSrqRzPw7fn2_rfAv7&usp=sharing).
60th Street Detour Map- December 6--7, 2020
Procter Extension Detour Map- December 6--7, 2020
Taft Avenue Detour Map- December 8--9, 2020
32nd Street Detour Map- December 8--9, 2020
Terrell Street Detour Map- December 9--10, 2020
Pinetop Road Detour Map- December 15--16, 2020